In order that construction work can continue effectively and safely in periods of insufficient natural light, it is important that a site is fitted with suitable artificial lighting. Lighting can be used internally for general movement and working on the site itself, externally for illuminating entry, storage and circulation areas, and can also be an effective form of deterrent for trespassers.
There are a wide range of lamps available, from simple tungsten filament lamps to tungsten halogen and discharge lamps. Site lighting is generally run off mains electricity at a voltage of 230 V, rather than through the use of generators. Sometimes it can be necessary to reduce the voltage to 110 V.
[edit] Lighting plan
For an appropriate lighting plan to be drawn up, the types of activity that will be likely to require lighting need to be specified. These activities can then be given an illumination target (with the unit being lux). Lamps are often given a measurement in lumens (lm), which is the total quantity of visible light emitted. One lux is one lumen per square metre.
Examples of recommended minimum target values for building activities include:
External lighting:
- Circulation: 10 lx
- Materials handling: 10 lx
Internal lighting:
- Circulation: 5 lx
- Working areas: 15 lx
- Concreting: 50 lx
- Carpentry and joinery: 100 lx
- Bricklaying and plastering: 100 lx
- Painting and decorating: 200 lx
- Site offices: 200 lx
- Drawing board positions: 300 lx
While manufacturers will often specify the best arrangement for lamps according to required use, it is common practice to plan for at least twice the recommended target values. This is because lamps in use can be subject to deterioration, dirt or other conditions that reduce their performance.
It is possible to calculate the required lumens for a particular need with the following equation:
Total lumens required = area to be illuminated (m2) x target value (lx) / Utilisation factor
Where the utilisation factor is 0.23.
Once the lamp type has been chosen, the required number can be calculated with the following equation:
No. of lamps required = total lumens required / lumen output of lamp
[edit] Site arrangement
Lighting can be arranged on site in a static formation, where lamps are fixed to support poles, masts or items of plant such as scaffolding and tower cranes, or, it can be arranged locally, as and where work is progressing, by the use of moveable supports or being hand-held with trailing leads.
Walkways are often illuminated by bulkhead lamps on standard mains voltage. Bulkhead lamps have a die-cast aluminium alloy body together with a vandal-resistant translucent polycarbonate diffuser.
To illuminate general working areas, festoon (overhead) lighting can be suspended from grids at regular spacings. These are usually tungsten filament bulbs, and both cable and lampholders must be appropriately weather-resistant.
The arrangement must be such that visual intrusion and light spillage are kept to a minimum, particularly in close proximity to residential properties and busy roads where it may cause nuisance or distraction. Where necessary, lighting should be provided to site boundaries to ensure the safety of passing pedestrians.
For more information, see How to work safely on a construction site in the dark.
[edit] Related articles on Designing Buildings Wiki
- BREEAM Reduction of night time light pollution.
- Colour Rendering Index CRI.
- Construction phase plan.
- Daylight factor.
- Daylight lighting systems.
- Ergonomics in construction.
- General lighting v task lighting.
- How to work safely on a construction site in the dark.
- Improving visibility and resilience of buried services.
- Health and safety.
- Light obstruction notice.
- Light pollution.
- Lighting.
- Pre-construction information.
- Rights to light.
- Site appraisal.
- Site information.
- Site layout plan for construction
- Site plan.
- Site facilities.
- Site office.
- Site safety.
- Site storage.
- Site survey.
- Temporary site services.
- Welfare facilities.
[edit] External references
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann (2007)
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments